Line Efficiency: What 81% Tells You and What It Doesn't

An open notebook of handwritten figures with a stopwatch on the page, a pencil, a stack of folded garments, a measuring tape, scissors, thread and buttons on a slate-green background

“The line ran at eighty per cent today.” Everyone on the floor nods. But eighty per cent of what, measured how, with which people counted? The percentage is easy to produce and very easy to get wrong, and a line manager who trusts a wrong one will spend months fixing the wrong thing.

What the number actually is

Line efficiency compares two quantities of time:

  • Minutes available — operators × hours worked × 60.
  • Minutes earned — garments produced × SAM, the standard minutes it should take to make one garment.

Efficiency is minutes earned divided by minutes available. It says how much of the paid machine time was turned into finished work at the standard rate.

A worked example

These figures are made up to show the sum. They are not a benchmark and not a claim about any line. They are the values the production efficiency calculator opens with, so you can check them there.

  • 12 operators, 8 hours each
  • SAM: 18 minutes per garment
  • 260 good garments produced

Available: 12 × 8 × 60 = 5,760 minutes. Earned: 260 × 18 = 4,680 minutes. Efficiency: 4,680 ÷ 5,760 = 81.3%.

At 100% the same line would have made 5,760 ÷ 18 = 320 garments, so it was 60 short. The 1,080 minutes that were not earned are 18 hours of paid machine time — two and a quarter operators' full days. That is the figure worth taking to the floor: not “eighty-one per cent” but “eighteen hours of sewing we paid for and did not get.”

Four ways the percentage goes wrong

1. A SAM nobody measured

Everything above depends on the 18. If it came from a buyer's sheet, a catalogue or a guess, the efficiency is only as good as that number. Same line, same 260 garments, only the SAM changes:

  • SAM 15: 3,900 minutes earned, 67.7%.
  • SAM 18: 4,680 minutes earned, 81.3%.
  • SAM 21: 5,460 minutes earned, 94.8%.

Twenty-seven points between the lowest and the highest, with not one garment more or fewer sewn. A figure above 100% almost always means the SAM is too generous, not that the line beat the standard.

2. Counting rejects as produced

Only good pieces count. If those 260 garments include 15 that have to be redone, the good ones are 245: 245 × 18 = 4,410 minutes earned, and efficiency is 76.6%. Counting the rejects flattered the line by almost five points.

3. Counting the wrong people

Operators means people who sew. Helpers, checkers and the supervisor should be left out unless they are on a machine. Count two helpers as operators and the available time becomes 14 × 8 × 60 = 6,720 minutes, so the same output reads 69.6%. The line did not get worse; the denominator got bigger.

4. Counting hours nobody sewed

Use paid hours actually on the machine. If the eight hours include an unpaid half hour for tea, the real figure is 7.5 hours: 12 × 7.5 × 60 = 5,400 minutes, and the same output is 86.7%.

Write down the rules once Who counts as an operator, which hours count, whether rejects count, where the SAM came from. Then use the same rules every day. A lower number measured the same way is more useful than a higher number measured differently each time.

What the number cannot tell you

Efficiency says how much was lost. It does not say why. Machine breakdowns, waiting for cut parts and style changeovers all appear as the same missing minutes, and they have different fixes: a mechanic, the cutting room, the planning desk.

So when you find the missing minutes, do not stop at the percentage. For one week, have each line supervisor write down every stoppage and what caused it, even roughly. At the end of the week there is a short list, and the biggest item on it is where to start. You may find that the line is losing more waiting for cut parts than to anything on the machines — in which case the answer is in the cutting room, not on the sewing floor.

Why it reaches the price

The day's wages do not change when output falls. At 260 garments each one carries one 260th of them; at 320, one 320th — 18.75% less labour on every garment. Efficiency is therefore part of what a garment really costs, and the costing sheet that prices it will be wrong if its stitching cost was worked out on a good day.

What these sums leave out

  • Output is not the only measure. A line can hit its efficiency by making garments that fail inspection later; that is why rejects are taken out above.
  • One day proves little. A new style, a power cut or a short fabric delivery can move a single day by ten points. Look at a week.
  • There is no number to aim at. Another unit's percentage, measured with its own SAM and its own rules, tells you nothing about yours. Compare a line with itself, week on week.

Put your own figures into the calculator; it shows the minutes available, the minutes earned, the output at 100% and the shortfall, so the percentage is never the only thing on the screen. If the missing minutes turn out to be in the cutting room, the cutting wastage article is the next place to look.

Read next

Related guides

What Trims Really Cost per Garment
Business

What Trims Really Cost per Garment

Buttons come in packs and labels have a minimum. Work out what trims cost per garment from what you must buy, and why a smaller order pays more per piece.

What a 60-Day Payment Term Really Costs
Business

What a 60-Day Payment Term Really Costs

You pay for fabric and wages now and are paid in sixty days. What the wait costs per garment and per order, and when an early-payment discount pays.