When a line finishes one style and starts the next, the machines do not stop for a clean break. Threads are changed, guides are set, the first pieces go slowly and the line takes time to settle. That time is paid for, and it is shared across the garments of the new order.
Where the time goes
- The stop: the hour in which the line makes nothing while it is set up.
- The slow start: the hours after, when the line runs below its standard.
A worked example
These figures are made up to show the sum. They are not a benchmark and not a claim about any style or any unit. The line is the one in the cut-and-make rate article: 12 operators at ₹400 an hour and an assumed ₹15,000 a day for power, rent and the rest, over 8 hours, making 260 garments a day. One hour of that line costs 12 × ₹400 + ₹15,000 ÷ 8 = ₹6,675.
Say the change stops the line for 1 hour, and for the next 2 hours it runs at 70% of its usual output. The lost time is 1 + 2 × 0.3 = 1.6 line hours.
- Cost of the change: 1.6 × ₹6,675 = ₹10,680.
- Garments not made: 260 ÷ 8 × 1.6 = 52.
Spread over the order
The same ₹10,680 is a different amount a garment, depending on the order it starts:
- 500 garments: ₹21.36 each.
- 1,000 garments: ₹10.68 each.
- 2,000 garments: ₹5.34 each.
- 5,000 garments: ₹2.14 each.
If the line changes style three times in a week, that is 3 × ₹10,680 = ₹32,040 of line time, whatever the quantity. This is the same effect the minimum order quantity article found for setup cost, seen from the shop floor.
Small orders carry the change
The change costs the same for 500 garments as for 5,000. On the small order it is ten times as much for each garment.
What to do with it
- Time the last change. Note when the old style stopped and when the new one reached its standard output.
- Put it in the quote. Divide the cost of the change by the order quantity and add it as its own line.
- Group similar styles. Two styles that need the same thread and the same machines cost less to change between.
- Keep the step ready. Threads, guides and the first pieces set up before the old style ends make the stop shorter.
What the sums leave out
- Made-up numbers. The 1 hour, the 70% and the 2 hours are assumptions. Time your own.
- Rejects in the first pieces. They are in the rejects article, not here.
- Different lines. A line with a slow step loses more when it restarts, as the line balancing article shows.
Put your own people, hours and output into the production efficiency calculator to find what an hour of your line costs, then multiply by the time your last change took.